Ongoing Construction of New Berth at Mtwara Port
Latest Tanzania transport news · Ongoing Construction of New Berth at Mtwara Port explained · updated Aug 19, 2026 · sports news · match · score
TLDR
- The construction of a new berth at Mtwara Port is currently underway, with the project at 44% completion and expected to finish next year.
- The new berth will be 300 meters long and 15 meters deep, designed to handle bulk cargo such as cement and coal.
- Since February, Mtwara Port has serviced 23 vessels and 6,390 vehicles, indicating increased shipping activity.
- The port expansion has improved economic opportunities for local residents and transport stakeholders, reducing shipping costs to neighboring countries.
- Mtwara Port, established in 1950, has increased its berths from three to four to accommodate larger vessels and more cargo.