Improvements Observed in Tegeta Road Construction Under DMDP II
Latest Tanzania construction news · Improvements Observed in Tegeta Road Construction Under… explained · updated Aug 21, 2026 · breaking news · latest updates · explained
TLDR
- The Chief Executive Officer of TARURA, Engineer Victor Seff, reported intensified monitoring of contractor CRC due to delays in road construction projects under DMDP II.
- During a recent inspection, TARURA noted improvements on the Tegeta road, where over 500 meters have been concreted.
- Compensation issues are still affecting the remaining section of the Tegeta road, with payments pending approval from the Chief Government Valuer.
- In Kinondoni, the pace of implementation has increased by approximately 10 percent since the last inspection, but the contractor may not meet the scheduled completion timeframe.
- The contractor has requested an extension of the implementation period due to asphalt availability and unpaid compensation areas, which will be assessed by the supervising consultant.