Government Commitment to Improve Transport Infrastructure for Enhanced Citizen Services

Latest Tanzania transport news · Government Commitment to Improve Transport Infrastructu… explained · updated Aug 18, 2026 · sports news · match · score

TLDR

  • The rehabilitation of Kigoma Airport has reached 67% completion and is expected to be finished by December 5, 2026.
  • The project, valued at 51.4 billion Tanzanian Shillings, aims to enhance air transport services and economic opportunities in the region.
  • Transport Minister Prof. Makame Mbarawa reported the progress during a site visit on August 15, 2026, noting an increase in completion from 61% to 67% within a month.
  • 80% of the necessary materials for the rehabilitation have already arrived, with the remaining items being aircraft navigation lights expected in two months.
  • The contractor has been paid 23 billion Shillings, with an additional payment of 1.23 billion Shillings pending at the Ministry of Finance.