Completion of 400-kV Power Transmission Line from Chalinze to Dodoma
Latest Tanzania energy news · Completion of 400-kV Power Transmission Line from Chali… explained · updated Aug 19, 2026 · energy news · power · electricity
TLDR
- The 400-kilovolt (kV) electricity transmission line from Chalinze to Dodoma has been completed.
- This project allows power generated at the Julius Nyerere Hydropower Plant (JNHPP) to reach Dodoma.
- The transmission line covers a distance of 345 kilometers.
- Construction of the transmission line is 99 percent complete, while the expansion of the Zuzu Substation is 98 percent complete.
- Trial energisation at the Zuzu Substation is set to begin soon, enabling electricity flow to Dodoma.